What the delays at the Building Safety Regulator mean for high-rise development

shutterstock_2581053815

The new system of gateway checks on high rise buildings is adding anything up to 18 months to construction programmes. Joey Gardiner finds out why

Last month student housing giant Unite broke cover about what is now one of the biggest issues facing developers of high-rise residential buildings in England. In a trading update, the firm revealed that delays caused by the “new approval gateways” policed by the new building safety regulator (BSR) were forcing it to add “around six months” to project timelines.

Unite is by no means alone. David O’Leary, executive director for policy at the Home Builders’ Federation, says some of the industry group’s members have reported waits of a year or more for approval. In the construction industry, of course, time is money, and there is mounting frustration across the sector over an issue that some say is having a profound impact on the development of high-rise resi schemes.

“This is huge,” says O’Leary. “It’s right up there with the biggest issues the industry is facing.”

Login or Register for free to continue reading Housing Today

To continue enjoying housingtoday.co.uk, REGISTER FOR FREE

Already registered? Login here

Stay at the forefront of thought leadership with news and analysis from award-winning journalists. Sign up below to receive:

  • Breaking industry news as it happens
  • Gain access to Housing Today’s Specialist CPD modules
  • Expert News and analysis

It takes less than one minute….

Join the Housing Today community - REGISTER TODAY

… or subscribe for full access - Subscribe now